Aircraft Parking Apron Contract # F38604-03-T-0559
Brief Project Scope of Work
General Site Works: Survey the area for the proposed asphalt pavement, underground utilities (such as; inlet structure, new storm manhole, culverts, fire protection line etc) and the location of exterior electrical works. Clear all obstruction, demolish tress within 20m of apron edge and level the ground.
Construction of Aircraft Apron pavement (50,000m2): Grade, level and compact the sub-grade. Bury all existing communication and power lines including conduits required. Construct the concrete pavement by; Install polyethylene sheet layer, formworks & dowels. Pour concrete in the panel – alternate sequence, curing. Construct expansion joints. Lay asphalt on the apron driveway. Provide pavement marking.
Underground utilities: Provide & install fire fighting system including gate valves, fire hydrants etc., install under ground irrigation line, storm drainage system. Provide and install communication and power lines including testing & commissioning.

Client:
U.S. Air force
Location:
Sheikh Issa Air Base, Bahrain
Contractor:
Diva for Trading and Contracting
Construct Depot Supply Warehouse Contract # F33600-99-C-0028
Brief Project Scope of Work
The project includes the design and construction of 4 nos. Warehouse (pre-engineered steel buildings – approx. area 15,000 m2). The 4 numbers warehouses includes the following: Earthwork, RCC foundation, RCC grade beam, RCC floor slab with expansion and construction joints, etc., Design and erection of pre-engineered steel building Office area 340 m2 including furniture Design and install of HVAC system. Design and install fire detection, prevention & fighting system. Generators (4 nos.) including generator shelter, electrical and fueling network. Automated shelving system including tire racks.
Epoxy quoted floor. Plumbing and sewage system including lift stations. External electrical and security network. Development of a perimeter road and parking areas approx. 8,750 m2 which includes scarifying/excavating existing grade 45 cm depth; deliver and grade base course, compact in 10 – 15 cm lifts; apply tack and prime coat; deliver, place and compact 5 cm lifts of asphalt wearing course; compact asphalt pavement. Supply and install communication system for the offices inside warehouse. Provision of office furniture and equipments.

Client:
U.S. Air force
Location:
KAAB, Dhahran
Contractor:
Diva for Trading and Contracting
Indefinite Delivery Indefinite Quantity (IDIQ) Trailers GCC countries, Afghanistan & Iraq Contract # F38604-09-RA006
Brief Project Scope of Work
Supply and installation of 50 each, 2-storey and 83 each, 1-storey complex/latrine trailers with varying sizes. These modular trailers will be fabricated off site and will be installed in Airbase together with exterior skirting. The skirting, concrete landing and exterior steel stair & landing will be designed and will be installed at necessary height on door opening as per specification. The skirting will have vent louver and access doors.
HVAC system will be furnished on the building where the compressor units and will be installed at exterior concrete pads. Grounding system was provided for the equipment and modular building. All required new utility system will be hooked up to existing utilities. Fabrication off site, on site work necessary to construct foundations and connect to utilities, transportation from the fabrication yard to the site, placement of the facility on foundations, connect to utilities and other pertinent works to provide a complete and usable dry stock modular facility offices, 16 ft. by 46 ft. (24 each) Furnish and install double storey 16 room dormitory facilities (16 nos.). The facility shall contain 2 rows of rooms separated by a hallway. It contains a shower and latrine facility on each floor. Each room will be 16’ x 12’ in size. The facility will include fire fighting system, fire sprinkler heads, piping system and fire panel system. The facilities shall be equipped with all utilities such as water sewer, electrical and communication system. The single storey dormitory facility (16 man sleeper) 56 each.

Client:
380 ECONS – U.S. Air force
Location:
Al Dhafra Air Base, Abu Dhabi, U.A.E
Contractor:
Diva for Trading and Contracting
Air Field Pavement (Runways / Taxi-ways)
Brief Project Scope of Work
DIVA FOR TRADING AND CONTRACTING was awarded a two (2) Million U.S. Dollars Airfield paving contract in 2000. The contract scope of work was to build taxi-ways and runways for the British Royal Air Force in Dhahran Air Base. The work included cut and fill operations, preparation of sub-grades according to standard specifications, and placing the designed concrete pavement thickness which was reinforced with two layers of steel reinforcement mesh. Due to weather condition and urgency nature of the job, special admixtures and concrete additives were included in the concrete mix to speed up the hardening process and to help in reaching the required concrete strength in specified time. Our completion of all tasks was remarkably recognized by our client.

Client:
British Royal Air Base, Saudi Arabia
Location:
Dhahran Air Base, Saudi Arabia
Contractor:
Diva for Trading and Contracting
Repair main Entry Road Contract # F38604-02-CX001
Brief Project Scope of Work
Demolition of existing main entry road. Supply and construct main entry asphalt road. Supply of lumbers, nails and other construction items. Supply and install Jersey and crash barriers. Supply and install Texas barriers. Supply and install traffic control & bollards.

Client:
British Royal Air Base, Saudi Arabia
Location:
Dhahran Air Base, Saudi Arabia
Contractor:
Diva for Trading and Contracting
Pasni Air Field Repairs Contract # DACA 78-02-R-0027
Brief Project Scope of Work
Dismantling of concrete pavement and runway along the center line and dispose of debris within 2 km haulage. Removal of 200 mm thick sand / gravel & disposal. Compaction & filling of gravel material, 300 mm thick. Provide & fixing steel dowels 20 mm dia. 405 mm long. Laying of ready-mix concrete in panel of 3.8m x 3.8 m at 250 mm thick having a compressive strength of 3500 psi over polyethylene sheet 50 micron thick at bottom. Providing, filling 13 mm sealant with backer rod material as per detail drawing & specification. Execute runway painting and airfield markings.

Client:
UAACE – Transatlantic Program Ctr. Winchester, VA
Location:
Pasni, Pakistan
Contractor:
Diva for Trading and Contracting
Rubber removal and re-stripe, Runway Contract # F38604-03-C-0005
Brief Project Scope of Work
Provide temporary markings and traffic controls on the work zones to establish safe working condition. Remove rubber and paint built up by using sand/abrasive materials injected in to high-pressure system. Clean the runway pavement area by water- jetting which is capable of discharging water flow of 8-9 gallons minute at 35,000 psi to 38,000 psi.
Provide water trucks for the supply of water necessary for this job. Clean up all debris, rubbish & waste accumulated during the removal process. Dispose off these waste materials. Prepare the specified procedure in testing the performance work i.e. to test the removal of 85-100% rubber and paint deposits. Paint the runway pavement according to the manufacturer standards and to the satisfaction of contracting officer.

Client:
379 AEW/ECONS
Location:
Al Udeid Air Base, Qatar
Contractor:
Diva for Trading and Contracting
Construct TASS Tower – 1 no. Contract # F38604-03-C0008
Brief Project Scope of Work
Civil Works: Design of the tower including accessories & its single foundation that can with sand wind gusts of up to 90 mph with minimal deflection. Surveying/layout, leveling & grading, excavation, concreting for foundation, damp proofing, backfilling. Supply and erect hot-dip galvanized steel, self- supporting, lattice-type telecommunication tower (Height: 30.5m with 3.86m x 3.86m base). Tower accessories include the installation of antenna mounts, ladder/climbing devices and work platforms located above 24.4m. Painting of the steel structure.
Electrical Works: Supply and install electrical works such as: obstruction lamps as per FAA regulation, copper cable XLPE/PVC with ground wire, cable clips, splice kits, termination kits, current transformer with relay, disconnect switch, panel boards with pilot lamp, timer etc. mounting of equipments which includes all antennae, receivers and other associated equipments.

Client:
379 AEW/ECONS
Location:
Al Udeid Air Base, Qatar
Contractor:
Diva for Trading and Contracting
Communication LMR Tower & Equipment Contract # F38604-03-C-0008
Brief Project Scope of Work
Surveying/layout the location of Modular shelter, tower foundation, manhole, and trenches. Prepare soil testing report. Design the RC foundation of Comm. Tower. Construct the equipment shelter which includes installation of RC foundation in position; fabricate modular building including interior finishes, electrical & HVAC works as per specification. Construction of Tower piers; which includes excavation of soil, compaction, lay polyethylene sheet and pour lean concrete; install formworks & steel reinforcement, install the anchor bolts and pour ready-mix concrete; apply bituminous coating and backfilling.
Perform exterior works such as; construction of electrical manhole, cable trenches, install 4” PVC pipe and pour concrete on duct banks, backfilling, provide and install MV & LV cables inside the trench, construct transformer & generator pads.

Client:
379 AEW/ECONS – USAF
Location:
Camp Al Udeid, Qatar
Contractor:
Diva for Trading and Contracting
TA-50 Wash Rack Contract # DASA04-02-C-0029
Brief Project Scope of Work
Survey the area; excavate soil for foundation of steel column. Provide formwork for RCC ground slab and install epoxy-coated steel reinforcement. Pour ready-mix concrete.
Erect the steel structure for the sunshade. Install roof metal panel including steel gutter & downspout. Construct the wash basin and large & small work table. Install the required plumbing system. Install the drainage system underground. Paint the whole structure. Restore the asphalt pavement

Client:
USAF
Location:
Camp As Sayliyah, Qatar
Contractor:
Diva for Trading and Contracting
Construct Vehicle Sunshade – 2nos. Contract # DASA04-02-C-0028
Brief Project Scope of Work
Survey the area; excavate soil for foundation of steel column. Install formworks & steel reinforcement, pour concrete for RC spread footings. Cure the concrete and apply bitumen damp proofing. Backfill the area and restore the ground slope.
Restore the asphalt pavement. Erect the steel structure for the sunshade. Install roof metal panel including steel gutter & downspout.
Paint the whole structure. Install lighting fixtures including other electrical works with all the required conduits & wirings.
Install pre-cast concrete wheel stops & bollards. Construct access roads as per drawing which includes surveying works, scarifying the loose soils, compact & grade, laying of sub-base and base-course materials.

Client:
USAF
Location:
Camp As Sayliyah, Qatar
Contractor:
Diva for Trading and Contracting
Construction of HESCO Berm Wall Contract # F38604-T-0425
Brief Project Scope of Work
Survey the area to establish the elevation, profile and the layout of the proposed wall (approx length 120 meters).
Clear all obstruction. Grade, level and compact the ground that will receive the walls. Provide equipments and vehicles that will haul the materials for HESCO berm wall. Install the assembly of first layer of the wall in accordance with the recommended procedures of HESCO BASTIO Defense wall. Fill the first layer of the wall with sand and gravel. Construct the second layer of the wall and fill with sand. Clean up the area.

Client:
United States Air Force
Location:
Shaik issa Airbase, Bahrain
Contractor:
Diva for Trading and Contracting
Runway Rubber Removal Contract # F38604-T-0455
Brief Project Scope of Work
Provide temporary markings and traffic controls on the work zone to establish safe working condition. Remove rubber and paint build up by using sane/abrasive materials injected into high- pressure system. Clean the runway pavement area by water- jetting which is capable of discharging water flow of 8-9 gallons per minute at 35,000 psi to 38,000 psi. Provide water trucks for the supply of water necessary for this job.
Clean up all debris, rubbish & waste accumulated during the removal process. Dispose off these waste materials. Prepare the specified procedure in testing the performance work i.e. to test the removal of 85-100% rubber and paint deposits.

Client:
USAF
Location:
Shaik issa Airbase, Bahrain
Contractor:
Diva for Trading and Contracting
South Pol Bladder Farm Contract # F38604-03-R0001
Brief Project Scope of Work
Clear shrubs, level, grade the whole area approx. 100,000m2. Construct beam as per size specified in the drawing, this beam will have sand bedding 10 cm and the berm construction will be performed in layers. The bitumen (MC1) will be sprayed on the entire surfaces of berm for protection against erosion.
Construct road (920 linear meters) and Parking area (9,700m2). The uneven area will be backfilled, watered and compacted as per route mark. A 7 cm thick base course layer will be constructed and compacted up to 95%. Fabricate 14 sets double stairs and 16 sets single wooden stairs. Construct 3 sets of culvert including 30 cm dia. Pipe.

Client:
USAF
Location:
Shaik issa Airbase, Bahrain
Contractor:
Diva for Trading and Contracting
Upgrade Airfield Marking Contract # F38604-T-0421
Brief Project Scope of Work
Provide temporary markings and traffic controls on the work zones to establish safe working condition. Prepare the area to be painted. Clean the area by removing dust, dirt, poorly bonded paint and granular surface deposits using trisodium phosphate solution. Any visible signs of surface contamination will be removed by sweeping, blowing with compressed air or grinding. Rinse the area by water jetting. Test the pavement area for the moisture by employing the “Plastic wrap method” before marking execution. Perform the test stripe demonstration using proposed materials and equipments.
Mark the airfield pavement in accordance with all the requirement of the specification and to the satisfaction of the contracting officer.

Client:
United States Air Force
Location:
Shaik issa Airbase, Bahrain
Contractor:
Diva for Trading and Contracting
South ramp Taxiway Edge Lighting and Shoulders Contract # F38604-T-0467
Brief Project Scope of Work
Survey the area and clear all obstruction for the proposed asphalt pavement approx. 10,000 sqm. Grade, level and compact the sub grade. Lay base course material and compact to reach 95% compaction. Bury all existing communication and power lines including existing conduits as required.
Construct trenches, manholes, and duct bunk (PVC incased) along the route of the lighting. Pave the road/ shoulder (7.3) with asphalt by; applying bitumen coat, lay the 75mm binder course, apply the tack coat, lay the 50mm wearing course. Provide and install edge lighting fixtures including wiring and control cable for the communication and power lines. Construction of hand holes including the installation of grounding system.

Client:
United States Air Force
Location:
United States Air Force
Contractor:
Diva for Trading and Contracting
Concrete Barriers
Brief Project Scope of Work
The scope of this high profile contract included: Construction of 4.0 meter high “L” shaped concrete protection barriers. The barriers were built in 30 meter long sections. Each section was erected and placed according to specified plan for proper sheltering of Military facilities. Construction of Sun-shades and steel truss shelters for F-16 Air Crafts. Other protection facilities. DIVA FOR TRADING AND CONTRACTING construction teams completed all contract obligations and tasks according to schedule.
Client:
British Royal Air Force
Location:
British Royal Air Force
Contractor:
Diva for Trading and Contracting
Office Bldg. 110 Contract # DASA04-02-C-0030
Brief Project Scope of Work
Civil & Architectural works: Surveying/layout 6 nos. complexes. Total build up area 57,000 sqmter. Construct CMU perimeter wall up to 4 meter height and internal perimeter gypsum boards in metal studs, roof structure including acoustic drop ceiling. Install HM doors and roll-up doors. Painting of structures. HQ Building 15 mtr deep underground complete with anti explosion doors and windows.
Mechanical works: Supply and install HVAC system having a total cooling capacity of 4000 tons including all required ducting works & accessories. Electrical works: Installation of MDP distribution / panel boards to power the new office/supply areas from an existing electrical panel. Tying of new electrical panels into the existing distribution system. Exterior works: Construction of

Client:
ARCENT- QA
Location:
Camp As Sayliyah, Qatar
Contractor:
Diva for Trading and Contracting
Construct Latrines for Building 416 & 418 Contract # DASA04-02-C-0010
Brief Project Scope of Work
Civil & Architectural works: Surveying / layout, leveling & grading, excavation, concreting for foundation, damp proofing, backfilling, construct RC slab, supply and erect pre-engineered steel building complete with bathroom & toilet fixtures and laundry fixtures.
Mechanical works: Supply and install plumbing network (waterlines, sewer line, drainage & storm line). Supply and install 2 nos. Cooline package Air conditioning units having a cooling capacity of 25 tons, operated at 220V, 3ph, 50 hertz for each unit including ducting works.
Electrical works: Supply and install fluorescent fixtures, power receptacles, panel boards, grounding system, wires & cables, fire alarm & heat detectors. Exterior works: Excavation for waterline & Sewage line. Construct manholes 3 nos. Connect sewage system to lift station. Line & grade for walkway.

Client:
ARCENT- QA
Location:
Camp As Sayliyah, Qatar
Contractor:
Diva for Trading and Contracting
Building 218 – HVAC Upgrade Contract # DASA04-02-C-0027
Brief Project Scope of Work
Civil works: Construct concrete foundation pads of A/C units, transformers, and electrical panel board which include the surveying layout, leveling & grading, excavation, concreting, backfilling and restoration of the area.
Mechanical works (HVAC): Supply, transport and install the 16 nos. Al Zamil Cooline package air conditioning units having a cooling capacity of (20 Tons) 238 MBH (19.8TR) at 7500 CFM, operated at 380/415V, 3ph, 50 Hertz for each unit. Supply and installation of HVAC ducting made of galvanized sheet metal as per SMACNA specs. Including supports, insulation, duct liner, aluminum grillers & diffusers for supply and return lines. Electrical works: Design of one-line diagram for electrical system, dismantling & re-install the existing panel MDP, 3ph, 415/240 Volt, 50 hertz. Install GFCI furnished transformers. Supply and install 120mm2 direct buried cables (XLPE/PVC 1000 v grade), new switch board, Testing & commissioning.

Client:
ARCENT- QA
Location:
Camp As Sayliyah, Qatar
Contractor:
Diva for Trading and Contracting
New Public Affairs Office In Bldg. 406 Contract # DASA04-02-C-0027
Brief Project Scope of Work
Civil & Architectural Works: Surveying/ layout for PAO bldg. (size: 45.2m x 36.1m) and layout its boundary limits. Saw-cut and demolish existing flooring for divider wall & toilet. Excavate, lay base and course and compact for column foundation. Provide water barrier and pour lean concrete. Install formworks & rebar and pour ready-mix concrete. Construct RC column, apply bituminous coating on substructures, backfill and restore the floor slab. Construct CMU & gypsum board wall. Install acoustic ceiling, toilet accessories and provide floor & wall finishes. Install doors and paint all the structures.
Mechanical works: Supply and install exterior & interior drainage & waterlines and HVAC system. Electrical works: Installation of an interior electrical network and fire alarm system.

Client:
ARCENT- QA
Location:
Camp As Sayliyah, Qatar
Contractor:
Diva for Trading and Contracting
Public Affairs Office Communication Modification Contract # DASA04-02-C-0038
Brief Project Scope of Work
Electrical Works: Installation of Communication system for building 406 using ladder-type cable tray separating the telephone system from Data system wherein each office will have 6” x 6” x 6” painted with red color for data system. Both will have wall penetration of 2 inch diameter EMT pipe linking the 2 boxes to its own cable tray. The telephone cable trays (black color) are 4” lower than the cable tray (red color) at 10 feet high from above the finish floor level. All wall penetrations were provided with fire stop sealant.
Install 2 nos. framed data closet in Room 109. install 15 nos. double face plate for voice/data system, 40 nos. double-face plate for telephone system, 25 nos. for voice data combination, 2 nos. single face plate for voice only and 5 nos. single plate for data only (All the face plate will be installed in metallic box 2” x 4” 2 1/8” depth.

Client:
ARCENT- QA
Location:
Camp As Sayliyah, Qatar
Contractor:
Diva for Trading and Contracting
FY98 UMC Perimeter Security Improvements
Brief Project Scope of Work
The project scope of works includes the construction of five Guard Towers, Construction of sub-station transformer “P-8” building, construction of duct bunks and reinforced concrete manholes for electrical, power and communication systems. Included also the construction of perimeter asphalt road, site grading, placement and compaction of sub-base/base course, installation of kerb stone along the sides of the perimeter road, and application of tack/prime coat, delivery, placement/compaction of 5cm lift of asphalt mix and the installation of perimeter security lighting on top of the reinforced concrete fence.

Client:
U.S. Army Corps of Engineers
Location:
Navel Base, State of Bahrain
Contractor:
Diva for Trading and Contracting
Contingency Contract Force Protection
Brief Project Scope of Work
DIVA FOR TRADING AND CONTRACTING expertise and well trained groups were awarded a unique and strategic Force protection contract in September 2003. The contract scope includes: Design built Construction of ECP System (Entry Control Points) Construction of Concrete Barriers for perimeter Guide Rail Construction of anti-explosion walls. Construction of Guard Towers. Providing lighting system to perimeter fence.

Client:
U.S. Army Corps of Engineers
Location:
King Abdul Aziz Air Base, Dhahran
Contractor:
Diva for Trading and Contracting
Contingency Contract Renovation of Eagle Town
Brief Project Scope of Work
The contract was awarded a high profile renovation contract to accommodate U.S Army Forces in Dhahran, Saudi Arabia. The contingency renovation included: Construction and renovation of Architectural and Structural facilities. Upgrading of Lighting networks. Repair & supply of electrical High & Low Voltage Transformers. Renovation of Mechanical systems such as HVAC system & Plumbing system. Construction of parking area. Roofs repairs.

Client:
U.S. Army Corps of Engineers
Location:
King Abdul Aziz Air Base, Saudi Arabia
Contractor:
Diva for Trading and Contracting
Sewage Treatment Plant
Brief Project Scope of Work
Brown & Root Corp. Saudi Ltd. Is classified as one of the top Engineering Firms worldwide. DIVA FOR TRADING AND CONTRACTING and Brown & Root (Saudi Division) jointly participated in upgrading and maintaining the sewage treatment plant of the Dhahran Base in the Eastern Province. The scope of work included construction of a new big bond, a rotating bacterial primary tank, maintaining and clearing several sewage treatment facilities, and a training program for technician to operate the plant facilities. As a result of the successful joint effort between DIVA FOR TRADING AND CONTRACTING and Brown & Root, the two firms look forward for further cooperation.

Client:
U.S. Army Corps of Engineers
Location:
Dhahran Air Base, Saudi Arabia
Contractor:
Diva for Trading and Contracting
Contingency Contract Khobar Tower Repairs
Brief Project Scope of Work
Significantly strategic and challenging task was the repairing and rectifying of Al Khobar Towers after the major damage. DIVA FOR TRADING AND CONTRACTING well trained construction and maintenance groups were urgently authorized and directed to perform under extreme conditions of security and safety regulations to rectify the damage. The work tasks includes: Clearing and removing all construction, construction material, and furniture that were damaged and destroyed as a result of the explosion. Repairing and rectifying all damaged structure elements of the Towers. Replacing and rectifying all damaged electrical and mechanical works. Repairing and rectifying all architectural elements of the towers. Providing security and surveillance systems.

Client:
U.S. Army Corps of Engineers
Location:
Dhahran, Saudi Arabia
Contractor:
Diva for Trading and Contracting
Clearing Fire Ranges K.K.M.C
Brief Project Scope of Work
Due to confidentiality matters and urgency to perform under extreme conditions, company professional work groups were recommended to participate with explosive ordinates disposal (EOD) experts and consultants in preparing and clearing fire ranges for the U.S Army Training fields. Artillery and tank shells as well as Air-Bombing produce, after explosion, live ammunition shell fragments with sharp and thin metal edges, and metal balls which are classified as extremely harmful. Our company’s trained teams have successfully performed their tasks and were favorably recognized by our client.
Client:
U.S. Army Corps of Engineers
Location:
Eastern Province, Saudi Arabia
Contractor:
Diva for Trading and Contracting
Patrol Craft Fast Training Facility
The scope of the contract included
All concrete foundations and steel structure elements for 6300 square meter building area. All exterior and interior finishes according to the US codes and contract specifications. All HVAC, Fire protection system and all electrical and mechanical works. Cut and fill works including parking area. Developing 20,000 square meter parking area including side walks and bituminous paving. Landscaping and chain link fence. Provision of chilled water plant, sewage lift station and repair of existing pump station.

Client:
U.S. Army Corps of Engineers
Location:
Ras-Al-Ghar, Saudi Arabia
Contractor:
Diva for Trading and Contracting
Beljurashi General Hospital (200 Bed) Contract # 4661/4/29
Brief Project Scope of Work
Civil/Architectural works: surveying, earthworks, soil treatment, concreting, masonry works (tile/marble setting, CHB laying, plastering), waterproofing & insulation, steel & carpentry works, bathroom and toilet accessories, finishing (doors & windows installation, carpet, signage), painting, landscaping, asphalting etc.,
Electrical works: Interior and exterior electrical works (wires & cables, conduits, outlet & boxes, lights, switches, panel boards), grounding & lighting system, fire detection & suppression system, data and communication system. Mechanical works: Plumbing system (hot & cold waterlines, drainage & storm system, sewage & sanitary network, fire sprinkler system), boilers & tanks, medical gases piping network, HVAC system, diesel generators, water purification system, sewer treatment plant, irrigation system, elevators, steam lines & kidney equipments.

Client:
Saudi Government
Location:
Beljurashi City, K.S.A.
Contractor:
Diva for Trading and Contracting
Badr Al-Janoub Hospital (50 Bed) Contract # 5953/4/29
Brief Project Scope of Work
Civil/Architectural works: surveying, earthworks, soil treatment, concreting, masonry works (tile/marble setting, CHB laying, plastering), waterproofing & insulation, steel & carpentry works, bathroom and toilet accessories, finishing (doors & windows installation, carpet, signage), painting, landscaping, asphalting etc.,
Electrical works: Interior and exterior electrical works (wires & cables, conduits, outlet & boxes, lights, switches, panel boards), grounding & lighting system, fire detection & suppression system, data and communication system. Mechanical works: Plumbing system (hot & cold waterlines, drainage & storm system, sewage & sanitary network, fire sprinkler system), boilers & tanks, medical gases piping network, HVAC system, diesel generators, water purification system, sewer treatment plant, irrigation system, elevators, steam lines & kidney equipments.

Client:
Saudi Government
Location:
Najran – K.S.A.
Contractor:
Diva for Trading and Contracting
Namira Hospital (50 Bed) Contract # 4714/4/29
Brief Project Scope of Work
Civil/Architectural works: surveying, earthworks, soil treatment, concreting, masonry works (tile/marble setting, CHB laying, plastering), waterproofing & insulation, steel & carpentry works, bathroom and toilet accessories, finishing (doors & windows installation, carpet, signage), painting, landscaping, asphalting etc.,
Electrical works: Interior and exterior electrical works (wires & cables, conduits, outlet & boxes, lights, switches, panel boards), grounding & lighting system, fire detection & suppression system, data and communication system. Mechanical works: Plumbing system (hot & cold waterlines, drainage & storm system, sewage & sanitary network, fire sprinkler system), boilers & tanks, medical gases piping network, HVAC system, diesel generators, water purification system, sewer treatment plant, irrigation system, elevators, steam lines & kidney equipments

Client:
Saudi Government
Location:
Qunfudah – K.S.A.
Contractor:
Diva for Trading and Contracting
Haditha Hospital (50 Bed) Contract # 5954/4/29
Brief Project Scope of Work
Civil/Architectural works: surveying, earthworks, soil treatment, concreting, masonry works (tile/marble setting, CHB laying, plastering), waterproofing & insulation, steel & carpentry works, bathroom and toilet accessories, finishing (doors & windows installation, carpet, signage), painting, landscaping, asphalting etc.,
Electrical works: Interior and exterior electrical works (wires & cables, conduits, outlet & boxes, lights, switches, panel boards), grounding & lighting system, fire detection & suppression system, data and communication system. Mechanical works: Plumbing system (hot & cold waterlines, drainage & storm system, sewage & sanitary network, fire sprinkler system), boilers & tanks, medical gases piping network, HVAC system, diesel generators, water purification system, sewer treatment plant, irrigation system, elevators, steam lines & kidney equipments.

Client:
Saudi Government
Location:
Qurrayat– K.S.A.
Contractor:
Diva for Trading and Contracting
King Abdul Aziz Hospital (200 Bed) Contract # 4662/4/29
Brief Project Scope of Work
Civil/Architectural works: surveying, earthworks, soil treatment, concreting, masonry works (tile/marble setting, CHB laying, plastering), waterproofing & insulation, steel & carpentry works, bathroom and toilet accessories, finishing (doors & windows installation, carpet, signage), painting, landscaping, asphalting etc.,
Electrical works: Interior and exterior electrical works (wires & cables, conduits, outlet & boxes, lights, switches, panel boards), grounding & lighting system, fire detection & suppression system, data and communication system. Mechanical works: Plumbing system (hot & cold waterlines, drainage & storm system, sewage & sanitary network, fire sprinkler system), boilers & tanks, medical gases piping network, HVAC system, diesel generators, water purification system, sewer treatment plant, irrigation system, elevators, steam lines & kidney equipments.

Client:
Saudi Government
Location:
Skaka, Jouf – K.S.A.
Contractor:
Diva for Trading and Contracting
Hospital Maintenance
Brief Project Scope of Work
DIVA FOR TRADING AND CONTRACTING was awarded a three years contract from the Saudi Ministry of Health to provide general maintenance for Eastern Province Health centers. The scope of work included maintenance of all Architectural, Mechanical, Electrical and Landscaping facilities of the according program. completed budget programs.

Client:
Ministry of Health
Location:
Eastern Province, Kingdom of Saudi Arabia
Contractor:
Diva for Trading and Contracting
Four Star Hotel Project
Brief Project Scope of Work
The project includes the construction of 26 storey building with 3 basements in Seef District Bahrain. The major work is deep excavation up to – 15 mtrs. With sheet pilling and dewatering system and RCC cast – in – place piles.
The building consists of RCC framed structure with precast slabs. It includes complete exterior & interior finishes work of guest rooms, toilets, kitchen and other related items. It also includes complete electro mechanic work HVAC system, CCTV, communication system paging system, security system, fire alarm and protection system.
The exterior elevation consists of aluminum cladding. This building also includes interior and exterior car parking and vehicle inspection system.

Client:
Millennium Middle East Properties Co. W.L
Location:
Seef, Kingdom of Bahrain
Contractor:
Diva for Trading and Contracting
Saray Tower
The scope of the contract included
Construction of 20 storey building for Mr. Abdulmajeed K. Sapaan. Saray Tower is a perfect mixture of active and serene living. Its waterfront location makes it one of the most attractive residences in the area as well as its proximity to all of the vital destinations such as offices, hotels, malls, restaurants, etc.
The project was developed using the finest designs and materials in the market.

Client:
Abdulmajeed K. Sapaan
Location:
Juffair, Kingdom of Bahrain
Contractor:
Diva for Trading and Contracting
The Hotel Diva
Brief Project Scope of Work
The Hotel Diva features views of the magnificent Al Fateh Mosque and the azure waters of Manama Bay. It is a perfect mixture of active and serene living. Its location makes it one of the most attractive residences in the area as well as its proximity to all of the vital destinations such as offices, hotels, malls, restaurants, etc.
The project was developed using the finest designs and materials in the market.

Client:
The Hotel Diva
Location:
Juffair, Kingdom of Bahrain
Contractor:
Diva for Trading and Contracting
Al Dair Gardens for construction of 57 attached villas
The scope of the contract included
Construction of 57 attached villas at Al Dair Bahrain. The project is inclusive of around 500 mts. Road network including Sewage, Storm water and portable water lines. The villas are having high end finishings with modern design.

Client:
Akram Miknas
Location:
Al Dair, Kingdom of Bahrain
Contractor:
Diva for Trading and Contracting
Zanzibar Construction Facilities
Brief Project Scope of Work
This is one of DIVA FOR TRADING AND CONTRACTING International Ventures and Strategic Construction Projects. The project included construction of two Islamic mosques, two villas and residential quarters for consulate members, and ablution facilities. Although the construction operations were next to normal for our construction teams, yet the weather condition was considered unfavorable and presented one of the elements that affected the overall project schedule. The project included all architectural, electrical, mechanical and landscaping tasks for the above mentioned facilities.

Client:
Ministry of Finance
Location:
Zanzibar, Tanzania
Contractor:
Diva for Trading and Contracting
Promoseven Headquaters
The scope of the contract included
Construction of two 3 storey building for Promoseven headquarters. The project is for two different purposes, one for the office building and another one for the labour accommodation. The foundation was about 12m depth pile foundation and the office building is fully covered by glass cladding. The project is inclusive of around 100 mts road networks and all related infrastructure works.

Client:
Akram Miknas
Location:
Muharraq, Kingdom of Bahrain
Contractor:
Diva for Trading and Contracting
Eastern Province AMARA
Brief Project Scope of Work
A significant and challenging assignment to our maintenance department was the programming and planning of the general maintenance for 84 AMARA office buildings in 2000. Locations of all building were within the Eastern Province. However, some of the AMARA branch offices were located in very remote areas such as Al-Rub Al-Khali desert. With dedication to success our maintenance teams completed the assigned maintenance programs to the satisfaction of our client. The maintenance program for the 84 locations did not exceed budget limitations.
Client:
Govt. of K.S.A., Dammam Amara
Location:
Eastern Province, Saudi Arabia
Contractor:
Diva for Trading and Contracting
Fairmech Workshop Steel Structure
The scope of the contract included
All concrete foundations and steel structure elements for 2500 square meter building area. All exterior and interior finishes according to the BS codes and contract specifications. All HVAC, Fire protection system and all electrical and mechanical works. Cut and fill works including parking area. Developing 700 square meter parking area including side walks.

Client:
Akram Miknas
Location:
Askar, Kingdom of Bahrain
Contractor:
Diva for Trading and Contracting
ASKAR Store Steel Structure
The scope of the contract included
All concrete foundations and steel structure elements for 1800 square meter building area. All exterior and interior finishes according to the BS codes and contract specifications. All HVAC, Fire protection system and all electrical and mechanical works. Cut and fill works including parking area.

Client:
Akram Miknas
Location:
Askar, Kingdom of Bahrain
Contractor:
Diva for Trading and Contracting
Medium Wave Facility
Brief Project Scope of Work
The works involve utility connection from an existing S.W. Facility, located 2.50 kilometers away: 2.50 km. of 11kv electric distribution line, 3 core x 120 msq, medium voltage cable, xlpe/swa/pvc direct buried copper cable, anufactured by Gulf Cable, pre-cast concrete manholes, cable protective tiles, detectable warning ape, fine sand bedding and grounding system. The electric system include outdoor type MVA sub-station; primary voltage is 11,000 volts and secondary voltage of 4160 volts. There are 2 units, 12.5 kva step down transformer, from 4160 volts/380-220 volts; 4160 volts switch-gear array; 1kv oil switch load break for the main power transformer.
2.50 km. of 24 core, fiber optic cable, communication line, manufactured by Belden. It is inserted In 4 inch pvc conduit, sch. 80, with 1x36mmsq, stranded bare copper wire as grounding system. It is protected by detectable warning tape and cable protective tiles or bricks. It involves pre-cast Concrete manholes with heavy duty covers and complete grounding system. 2.50km, water line system, 2 inch pvc conduit sch. 80. it involves 4 nos. of gate valve and non-return valves. The pre-engineered building is manufactured by Kirby of Kuwait. It is 38 metersx26metersx7.20 meters high. It has HVAC, 2×2 tons carrier package air conditioning units, lighting and power system, power receptacles, lighting and power panel boards, UPS system, fire alarm and protection system, CCTV and communication system, raw water and distilled water system etc.

Client:
International Broadcasting Bureau, Washington D.C., U.S.A
Location:
Abdaly Road, State of Kuwait
Contractor:
Diva for Trading and Contracting
High Speed Train Connecting Egypt’s Ain Sokhna to Alamein
This railway line will link Ain Sokhna on the Red Sea coast and the new Alamein City on the Mediterranean coast in Egypt. The project is about Build, finance and operates an electric high-speed passenger and freight railway line. The 534-kilometre high-speed rail is to be developed using a combined engineering, procurement and construction (EPC) and financing model. This project comprises first phase of Egypt’s plan to build 2,000 kilometres of high-speed rail to complement its mainline network. Client has prequalified 10 consortiums for the contract to build, finance and operate this scheme. The Transport Ministry is studying offers from 23 local and international firms to build, operate and maintain a high-speed electric railway line linking Ain Sokhna to Al Alamein. A joint committee from the ministries of housing and transport is expected to conclude its review of the offers within a month, after which the government will begin receiving financial and technical offers. The 534-km line will accommodate both cargo and passenger trains, passing through the new capital, 6 October City, and Alexandria.

Client:
Egypt Government
Location:
Egypt
Contractor:
Diva for Trading and Contracting